Transmission Operator Eliminates Venting Across Seven Pig Launcher and Receiver Drawdowns Using ZEVAC Mobile Equipment

A contracted pipeline crew used ZEVAC cross-compression to completely eliminate venting and flaring across four launcher and three receiver drawdowns, capturing over 31,800 SCF of natural gas in the process.

Customer

North American Transmission Operator

Jobsite

Lupton, CO

Objective

Eliminate Emissions from Pigging Operations

Solution

ZEVAC Quad

31,803 SCF Methane Recaptured
18 Metric Tons CO2 Equivalent Saved
7 Drawdowns Without Emissions

THE CHALLENGE

A Routine Pigging Operation with Two Unavoidable Venting Events

Gas-Pipeline integrity management depends on pigging, the process of running specialized tools through pressurized pipelines for cleaning, deformation inspection, and in-line inspection (ILI). For gas transmission operators, it's one of the most frequent and operationally critical maintenance activities performed.

The challenge is structural: every standard pigging operation requires venting not once, but twice. To launch a pig, the pipeline must be opened to atmosphere and the launcher barrel depressurized. To receive the pig at the far end, the receiver site must also be fully depressurized before the hatch can be opened. Multiply that across multiple pig runs, cleaning, deformation, and ILI, and the cumulative venting volume becomes significant..

 "These projects were not in high-traffic urban areas but were still close to residential neighborhoods and would have required notifications of the venting/flaring activity  and expected complaints due to the noise it would have caused."

 

Mandatory Dual-Vent Exposure

Each pig run requires depressurization at both the launcher and receiver - two venting events per run, multiplied across multiple pig types (cleaning, deformation, ILI).


 

Proximity to Residential Areas

The Fort Lupton site was near residential neighborhoods, making atmospheric venting a public nuisance and notification concern even without a formal urban-area restriction.


 

High Gas Volume at Stake

Initial drawdown pressures of 600–712 psig across 4 launchers and 3 receivers represented a substantial volume of natural gas that would otherwise be lost to the atmosphere.


 

Emissions Reduction Commitment

The Transmission Operator's objective was to reduce emissions and prevent purging a large volume of gas, requiring a zero-vent approach across all launcher and receiver operations.


THE SOLUTION

Two ZEVAC Quad Units Replace Every Vent Event with a Closed-Loop Gas Recovery Operation

A contracted pipeline crew executed the drawdowns using two ZEVAC Quad units and two rented air compressors, with support from engineering and inspection partners. Instead of venting at the launcher and receiver sites, ZEVAC vacuumed the gas from each barrel and discharged it into an adjacent live section of pipe, eliminating atmospheric release entirely.

Unit placement was confirmed with the operator in advance, prioritizing ease of operation and a clear emergency exit path. After isolating the relevant drawdown and discharge valves, the crew installed valve trees to each valve connection. With compressors warmed up and hoses purged of air, operations proceeded on a tight schedule across three consecutive days plus a follow-up ILI run four days later.


Operation Log - All 7 Drawdowns

  • Launcher #1 (Cleaning Pig)
    Drawdown from 690 psig to 0.3 psig. Discharge held at 720 psig. Pig loaded manually and launched. Following a concern raised by the operator, the launcher was repressurized and the crew returned the following day.

    Drawdown time: ~1 hour
  • Launcher #1 Relaunch (Cleaning Pig)
    Drawdown from 597 psig to 0 psig. Discharge held at 710.1 psig. The same launcher barrel from Day 1 was successfully drawn down and the pig loaded and launched via tow line and telescopic forklift.

    Drawdown time: ~45 minutes
  • Receiver #1 (Cleaning Pig Recovery)
    Drawdown from 712 psig to 0 psig. Discharge held at 720 psig. Pig recovered. Initial inspection confirmed tool was clean enough to proceed with a deformation pig.

    Drawdown time: ~45 minutes
  • Launcher #2 (Deformation Pig)
    Drawdown from 597 psig to 0 psig. Discharge held at 710.1 psig. Following successful recovery of the cleaning pig, the crew set up in the same configuration as Day 2.

    Drawdown time: ~45 minutes
  • Receiver #2 (Deformation Pig Recovery)
    Drawdown from 664.5 psig to 0 psig. Discharge held at 730 psig. Deformation tool recovered. Initial inspection revealed only minor deformations — greenlighting the ILI tool run.

    Drawdown time: ~45 minutes
  • Launcher #3 (ILI Tool)
    Drawdown from 695.6 psig to 0 psig. Discharge held at 710.7 psig. Four days after the deformation pig run confirmed only minor anomalies and greenlighted the ILI tool run. The ILI tool was loaded and launched to perform a full in-line inspection of the pipeline's interior condition.

    Drawdown time ~1 hour
  • Receiver #3 (ILI Tool Recovery)
    Drawdown fron 672.8 psig to 0 psig. Discharge held at 717 psig. ILI tool recovered, cleaned, and inspected.

    Drawdown time: ~1 hour

Equipment & Site Configuration

Detail
Specification
ZEVAC units deployed 
 Two ZEVAC Quad Gen 4 units 
Air compressors  Two rented compressors (incl. VHP400) 
Drawdown scope ~600 psig (upstream tap)
Initial drawdown pressures 597–712 psig (varied by run)
Final drawdown pressures 0–0.3 psig (full depressurization)
Discharge pressures maintained
710–882 psig
Pig types deployed Cleaning pig, deformation pig, ILI tool 
Total project duration 3 active days + ILI follow-up (Day 7)

 


PROJECT RESULTS

Seven Drawdowns. Zero Venting. Zero Incidents. Zero Complaints.

All seven drawdowns were completed without significant delays or incidents. By eliminating venting entirely, the project also avoided the notification obligations, noise complaints, and community friction that traditional venting/flaring would have triggered near residential neighborhoods in Fort Lupton.

 

All venting and flaring eliminated - zero atmospheric methane release across all 7 drawdowns


 

No public nuisance complaints or community notifications required


 

Full depressurization achieved on every launcher and receiver - drawdown to 0–0.3 psig in all cases


 

Three pig types successfully deployed: cleaning, deformation, and ILI all recovered without issue


 

Scalable approach - methodology directly applicable to future pigging programs and sensitive-location deployments


ABOUT THE PRODUCT

ZEVAC Quad - High Volume Cross-Compression for Pigging and Maintenance Operations

The ZEVAC Quad is built for high-volume, time-sensitive gas recovery where multiple compression cylinders are needed to depressurize large-diameter or high-pressure launcher and receiver barrels quickly. Like all ZEVAC equipment, it uses pneumatic positive-displacement cross-compression to transfer gas from an isolated section into a live system with no combustion, no rotating components, and no electronics.

Key Product Features

  • Powered by compressed air - no external grid or combustion required
  • Positive-displacement cross-compression - handles 100% dry gas to 100% liquid service
  • No rotating crankshaft or drivetrain - linear compression only
  • Portable and field-deployable - connects via flex hose and standard fittings
  • Achieves 0 psig drawdown - including pipeline commissioning vacuum applications
  • Can be run in series or parallel to minimize drawdown times

Eliminate Methane from Your Next Pigging Project

Talk with a ZEVAC Rep and start your journey to zero emissions.